MTO Rossport Bridge Repairs

 

This project was similar to the Selim Hill hyw bridge, but with less space to operate. Due to space restrictions we had to build a special setup using a Casagrande hammer and rotator drill rigged on a custom made frame to fit into the confined area. The scope of work was to drill eight holes with a 40’ diameter and 4.5 m deep into bedrock.

 

Location:
Rossport, Ontario

Client:
LH North / MTO

Year:
2016

Duration:
3 months

Value:
$1,000,000.00

Market:
Transportation Contracting